Global Green Power PLC Corporation is a Philippine Company that develops BIOMASS grid connected, decentralized, renewable energy power plants utilizing sustainable biomass resources such as agricultural crop and food processing wastes.

2011 May 26 GPBUPI Stakeholder's Consultation

Green Power Bukidnon Philippines Inc. multi-sectorial stakeholder's consultation addressing Clean Development Mechanism and Environmental Compliance.

2011 May 26 GPBUPI Stakeholder's Consultation - Green Power Bukidnon Philippines Inc. multi-sectorial stakeholder's consultation  addressing Clean Development Mechanism and Environmental Compliance.

GPPPI Plant Site Development

2011 September: Civil Works commence at Barangay Cabalabaguan, Mina, Iloilo, Philippines for the GPPPI 35 MW biomass power plant

GPPPI Plant Site Development - 2011 September: Civil Works commence at Barangay Cabalabaguan, Mina, Iloilo, Philippines for the GPPPI 35 MW biomass power plant

Green Power Panay Philippines Inc. (GPPPI) Office

2011 October: Green Power Panay Philippines (GPPPI) Office and Laboratory becomes fully operational at Barangay Cabalabaguan, Mina, Iloilo, Philippines

Green Power Panay Philippines Inc. (GPPPI) Office - 2011 October: Green Power Panay Philippines (GPPPI) Office and Laboratory becomes fully operational at Barangay Cabalabaguan, Mina, Iloilo, Philippines

GPNEPI Groundbreaking Ceremony

Barangay Tabuating, Municipality of San Leonardo, Province of Nueva Ecija, Luzon region, Philippines.

GPNEPI Groundbreaking Ceremony - Barangay Tabuating, Municipality of San Leonardo, Province of Nueva Ecija, Luzon region, Philippines.

GPPPI Groundbreaking Ceremony

Barangay Cabalabaguan, Municipality of Mina, Province of Iloilo, Western Visayas region, Philippines.

GPPPI Groundbreaking Ceremony - Barangay Cabalabaguan, Municipality of Mina, Province of Iloilo, Western Visayas region, Philippines.

GGP Group President & CEO, Mr. David de Montaigne

GGP Group President & CEO, Mr. David de Montaigne -
21 OCTOBER 2011 - Global Green power PLC Corporation opens office in Maramag, Bukidnon on the Island of Mindanao
7 OCTOBER 2011 - Global Green Power PLC Corporation (GGPC) opens office in Tuguegarao City, North Luzon to deliver biomass power to Cagayan and Isabella Provinces
3 OCTOBER 2011 - Green Power Cagayan Philippines Inc., (GPCPI) finalizes the acquisition of 8 Hectares of land for 35 MW Biomass Power Plant
20 SEPTEMBER 2011 - Green Power Bukidnon Philippines Inc., complete the purchase of 7.6 Hectares of land for the construction of the GPBPI 35 MW Biomass Power Plant in Maramag, Bukidnon, Mindanao
16 SEPTEMBER 2011 - The Province of Cagayan, Tuguegarao City issue Provincial Authority for Green Power Cagayan Philippines Inc., to Construct and Operate 35 MW Biomass Fired Power Plant
12 AUGUST 2011 - Grid Impact Study (GIS) for Green Power Panay 35 MW capacity approved by National Grid Corporation of the Philippines (NGCP)
10 AUGUST 2011 - Global Green Power PLC publish "Open Letter" to His Excellency President Aquino III in National and Regional Newspapers regarding the Socio-economic benefits and lower cost of GGPC Biomass Thermal Energy than Coal and Oil to Consumers
8 AUGUST 2011 - Green Power Bukidnon Philippines Inc (GPBPI) receive Environmental Compliance Certificate for 35 MW Biomass Power Plant in Maramag, Bukidnon, Mindanao from the Department of the Environment and Natural Resources (DENR)
29 JULY 2011 - Maribeth de Montaigne President Global Green Power PLC Corporation issues letter to Philippine Congress, the Senate, Government Agencies, NGO's and the Office of the President regarding the benefits of Thermal Grid Connected Biomass Power
15 JULY 2011 - Global Biomass PLC Corporation start development and construction of manufacturing R&D facility for biomass processing equipment in Mina, Iloilo, Panay.
5 JULY 2011 - Green Power Nueva Ecija Philippine Inc (GPNEPI) sucsessfully complete complete Clean Development Mechanism (CDM) Multi-Sectoral Consultation
1 JULY 2011 - Green Power Nueva Ecija complete Geotechnical Engineering Investigation of their 35 MW Biomass Power Plant site in San Leonardo, Nueva Ecija on Luzon Island
27 JUNE 2011 -The Municipality of Alcala of Cagayan Province issued their resolution in favor of Green Power Cagayan Valley Philippines Inc; "APPROVING THE ESTABLISHMENT, CONSTRUCTION AND OPERATION OF A 35 MEGAWATT RENEWABLE ENERGY BIOMASS POWER PLANT"
21 JUNE 2011 - Green Power Panay submit their request for Philippine Designated National Authority (DNA) approval for Clean Development Mechanism (CDM) participation and benefits
18 JUNE 2011 - Green Power Bukidnon receive Municipality of Maramag resolution "APPROVING THE ESTABLISHMENT AND CONSTRUCTION OF A 35 MEGAWATT RENEWABLE ENERGY BIOMASS POWER PLANT IN THE MUNICIPALITY"
9 JUNE 2011 - Green Power Panay issued "Order of Finality" granting conversion of land from Agricultural to Industrial purposes enabling the construction of a total capacity of 35 MW Biomass Power Plants within the Municipality Mina, Iloilo, Panay
1 JUNE 2011 - Global Green Power PLC appoint Price WaterhouseCoopers Services LLP (PwC) to raise additional long term debt finance for their deployment of Renewable Energy generating assets in the Philippines.
27 MAY 2011 - Green Power Bukidnon hold multi-sectorial Clean Development Mechanism consultation in Maramag, Bukidnon, Mindanao for their 35 MW biomass power plant
24 MAY 2011 - Green Power Nueva Ecija contract SOILS INC. to complete Geotechnical and Foundation Engineering Services for the 2 X 17.5 MW PI & P2 biomass power plants in San Leonardo, Luzon..
15 MAY 2011 - Green Power Panay complete water well drilling at 400 ft to supply water sufficient for 35 MW biomass power plant development
13 MAY 2011 - Green Power Panay secures the first BUREAU OF CUSTOMS Certificate of Registration to be issued under the Renewable Energy Act of 2008 for their Green Power Panay 2 X 17.5 MW P1 & P2 biomass power plants.
21 APRIL 2011 Green Power Bukidnon appoint Preferred Energy Inc to process and secure Environmental Compliance Certificate (ECC)
18 APRIL 2011 - Green Power Bukidnon to issue a Request for Offers (RFO) to a list of seven pre-qualified Engineering Construction and Procurement contractors to build their 35 MW biomass power plant in Maramag, Bukidnon
18 APRIL 2011 - Green Power Negros to issue a Request for Offers (RFO) to a list of seven pre-qualified Engineering Construction and Procurement contractors to build their 35 MW biomass power plant in Sagay City, Negros Occidental
15 APRIL 2011 - Green Power Panay issues a Request for Offers (RFO) to a list of seven pre-qualified Engineering Construction and Procurement contractors to build a second 17.5 MW biomass power plant in Mina, Iloilo
Downloads
The e-copy of GGPC situationer paper is available for download. Click the link below to download.
Download File
Notice of Public Hearing
2011 JANUARY 27 - Energy Regulatory Commission (ERC) Notice of Public Hearing on the Joint Application of Green Power Panay Philippines Inc. (GPPPI) and Iloilo I Electric Cooperative (ILECO I) for the approval of the Electric Supply Agreement (ESA).   Click to View PDF File
2011 JANUARY 27 - Energy Regulatory Commission (ERC) Notice of Public Hearing on the Joint Application of Green Power Panay Philippines Inc. (GPPPI) and Iloilo II Electric Cooperative (ILECO II) for the approval of the Electric Supply Agreement (ESA).   Click to View PDF File
Register to receive GGPC updates
ENTER YOUR EMAIL ADDRESS
Oil Price Dashboard
Crude Oil Price by OIL-PRICE.NET
Coal - Weekly Index
  NEWC Index RB Index DES ARA Index
06-Jan-2012 114.30 105.87 110.23
30-Dec-2011 115.47 106.57 112.39
23-Dec-2011 112.85 106.36 111.58
16-Dec-2011 110.28 101.95 110.61
Coal Weekly Index by globalCOAL


PDF Print E-mail Bookmark and Share


17 December 2009 in The Manila Times

British firm’s second RP biomass project kicks off

Renewable energy firm Global Green Power PLC Corp. is set to put up the second of a dozen biomass plants in the Philippines. On the sidelines of UK-based Global Green’s groundbreaking ceremony for its 17.5-megawatt plant here, the company’s president, Devid de Montaigne, said they will be putting up generating capacity totaling 420 megawatts at a cost of about $1 billion over an eight-year period.

“All of the feasibility is being done for all of the projects. Each of the projects is 17.5-megawatts but expandable to 35-megawatts,” he said.

Global Green’s biomass plants will use farm refuse such as rice and corn husks to generate clean and renewable electricity. They will serve as base-load plants that can run round-the-clock unlike other renewable energy sources whose output depends on the weather.

The company will buy feedstock from local farmers at an undisclosed rate, and will deliver an estimated 900 direct and indirect jobs for each plant.

The company’s biomass project will involve three phases of 140 megawatts each. The first phase is targeted for completion in three years.

Government already gave the go signal for three of the company’s proposed power plants, which will be located in Panay, Nueva Ecija and Pangasinan.

The company started construction of its power plant in Panay island in May last year while its Nueva Ecija plant, which will cost $43 million, will be put up upon financial closing.

“It will take 18 months to construct the plant upon financial closing. So we’ve done all the preliminary bidding for all of the equipment now. We have several lenders offering us the funding. We’re just negotiating the best terms for our customers,” de Montaigne said.

But unlike its Panay facility, whose output has been contracted by distribution utilities in the area, the Nueva Ecija plant’s capacity will be sold directly to the grid once government approves the feed-in tariff for renewable energy sources.

The feed-in tariff is one of the incentives under the Renewable Energy Act of 2008. It calls for a pegged price of electricity sourced from renewable energy sources for 12 years and priority purchase and transmission of and payment from the power grid.

The National Renewable Energy Board is studying the incentive and hopes to come up with its recommendations, which will be subject to the approval of the Department of Energy and the Energy Regulatory Commission, by the first quarter of the year.

 
Copyright © 2007 Global Green Power PLC All rights reserved