Global Green Power PLC Corporation is a Philippine Company that develops BIOMASS grid connected, decentralized, renewable energy power plants utilizing sustainable biomass resources such as agricultural crop and food processing wastes.

2011 May 26 GPBUPI Stakeholder's Consultation

Green Power Bukidnon Philippines Inc. multi-sectorial stakeholder's consultation addressing Clean Development Mechanism and Environmental Compliance.

2011 May 26 GPBUPI Stakeholder's Consultation - Green Power Bukidnon Philippines Inc. multi-sectorial stakeholder's consultation  addressing Clean Development Mechanism and Environmental Compliance.

GPPPI Plant Site Development

2011 September: Civil Works commence at Barangay Cabalabaguan, Mina, Iloilo, Philippines for the GPPPI 35 MW biomass power plant

GPPPI Plant Site Development - 2011 September: Civil Works commence at Barangay Cabalabaguan, Mina, Iloilo, Philippines for the GPPPI 35 MW biomass power plant

Green Power Panay Philippines Inc. (GPPPI) Office

2011 October: Green Power Panay Philippines (GPPPI) Office and Laboratory becomes fully operational at Barangay Cabalabaguan, Mina, Iloilo, Philippines

Green Power Panay Philippines Inc. (GPPPI) Office - 2011 October: Green Power Panay Philippines (GPPPI) Office and Laboratory becomes fully operational at Barangay Cabalabaguan, Mina, Iloilo, Philippines

GPNEPI Groundbreaking Ceremony

Barangay Tabuating, Municipality of San Leonardo, Province of Nueva Ecija, Luzon region, Philippines.

GPNEPI Groundbreaking Ceremony - Barangay Tabuating, Municipality of San Leonardo, Province of Nueva Ecija, Luzon region, Philippines.

GPPPI Groundbreaking Ceremony

Barangay Cabalabaguan, Municipality of Mina, Province of Iloilo, Western Visayas region, Philippines.

GPPPI Groundbreaking Ceremony - Barangay Cabalabaguan, Municipality of Mina, Province of Iloilo, Western Visayas region, Philippines.

GGP Group President & CEO, Mr. David de Montaigne

GGP Group President & CEO, Mr. David de Montaigne -
21 OCTOBER 2011 - Global Green power PLC Corporation opens office in Maramag, Bukidnon on the Island of Mindanao
7 OCTOBER 2011 - Global Green Power PLC Corporation (GGPC) opens office in Tuguegarao City, North Luzon to deliver biomass power to Cagayan and Isabella Provinces
3 OCTOBER 2011 - Green Power Cagayan Philippines Inc., (GPCPI) finalizes the acquisition of 8 Hectares of land for 35 MW Biomass Power Plant
20 SEPTEMBER 2011 - Green Power Bukidnon Philippines Inc., complete the purchase of 7.6 Hectares of land for the construction of the GPBPI 35 MW Biomass Power Plant in Maramag, Bukidnon, Mindanao
16 SEPTEMBER 2011 - The Province of Cagayan, Tuguegarao City issue Provincial Authority for Green Power Cagayan Philippines Inc., to Construct and Operate 35 MW Biomass Fired Power Plant
12 AUGUST 2011 - Grid Impact Study (GIS) for Green Power Panay 35 MW capacity approved by National Grid Corporation of the Philippines (NGCP)
10 AUGUST 2011 - Global Green Power PLC publish "Open Letter" to His Excellency President Aquino III in National and Regional Newspapers regarding the Socio-economic benefits and lower cost of GGPC Biomass Thermal Energy than Coal and Oil to Consumers
8 AUGUST 2011 - Green Power Bukidnon Philippines Inc (GPBPI) receive Environmental Compliance Certificate for 35 MW Biomass Power Plant in Maramag, Bukidnon, Mindanao from the Department of the Environment and Natural Resources (DENR)
29 JULY 2011 - Maribeth de Montaigne President Global Green Power PLC Corporation issues letter to Philippine Congress, the Senate, Government Agencies, NGO's and the Office of the President regarding the benefits of Thermal Grid Connected Biomass Power
15 JULY 2011 - Global Biomass PLC Corporation start development and construction of manufacturing R&D facility for biomass processing equipment in Mina, Iloilo, Panay.
5 JULY 2011 - Green Power Nueva Ecija Philippine Inc (GPNEPI) sucsessfully complete complete Clean Development Mechanism (CDM) Multi-Sectoral Consultation
1 JULY 2011 - Green Power Nueva Ecija complete Geotechnical Engineering Investigation of their 35 MW Biomass Power Plant site in San Leonardo, Nueva Ecija on Luzon Island
27 JUNE 2011 -The Municipality of Alcala of Cagayan Province issued their resolution in favor of Green Power Cagayan Valley Philippines Inc; "APPROVING THE ESTABLISHMENT, CONSTRUCTION AND OPERATION OF A 35 MEGAWATT RENEWABLE ENERGY BIOMASS POWER PLANT"
21 JUNE 2011 - Green Power Panay submit their request for Philippine Designated National Authority (DNA) approval for Clean Development Mechanism (CDM) participation and benefits
18 JUNE 2011 - Green Power Bukidnon receive Municipality of Maramag resolution "APPROVING THE ESTABLISHMENT AND CONSTRUCTION OF A 35 MEGAWATT RENEWABLE ENERGY BIOMASS POWER PLANT IN THE MUNICIPALITY"
9 JUNE 2011 - Green Power Panay issued "Order of Finality" granting conversion of land from Agricultural to Industrial purposes enabling the construction of a total capacity of 35 MW Biomass Power Plants within the Municipality Mina, Iloilo, Panay
1 JUNE 2011 - Global Green Power PLC appoint Price WaterhouseCoopers Services LLP (PwC) to raise additional long term debt finance for their deployment of Renewable Energy generating assets in the Philippines.
27 MAY 2011 - Green Power Bukidnon hold multi-sectorial Clean Development Mechanism consultation in Maramag, Bukidnon, Mindanao for their 35 MW biomass power plant
24 MAY 2011 - Green Power Nueva Ecija contract SOILS INC. to complete Geotechnical and Foundation Engineering Services for the 2 X 17.5 MW PI & P2 biomass power plants in San Leonardo, Luzon..
15 MAY 2011 - Green Power Panay complete water well drilling at 400 ft to supply water sufficient for 35 MW biomass power plant development
13 MAY 2011 - Green Power Panay secures the first BUREAU OF CUSTOMS Certificate of Registration to be issued under the Renewable Energy Act of 2008 for their Green Power Panay 2 X 17.5 MW P1 & P2 biomass power plants.
21 APRIL 2011 Green Power Bukidnon appoint Preferred Energy Inc to process and secure Environmental Compliance Certificate (ECC)
18 APRIL 2011 - Green Power Bukidnon to issue a Request for Offers (RFO) to a list of seven pre-qualified Engineering Construction and Procurement contractors to build their 35 MW biomass power plant in Maramag, Bukidnon
18 APRIL 2011 - Green Power Negros to issue a Request for Offers (RFO) to a list of seven pre-qualified Engineering Construction and Procurement contractors to build their 35 MW biomass power plant in Sagay City, Negros Occidental
15 APRIL 2011 - Green Power Panay issues a Request for Offers (RFO) to a list of seven pre-qualified Engineering Construction and Procurement contractors to build a second 17.5 MW biomass power plant in Mina, Iloilo
Downloads
The e-copy of GGPC situationer paper is available for download. Click the link below to download.
Download File
Notice of Public Hearing
2011 JANUARY 27 - Energy Regulatory Commission (ERC) Notice of Public Hearing on the Joint Application of Green Power Panay Philippines Inc. (GPPPI) and Iloilo I Electric Cooperative (ILECO I) for the approval of the Electric Supply Agreement (ESA).   Click to View PDF File
2011 JANUARY 27 - Energy Regulatory Commission (ERC) Notice of Public Hearing on the Joint Application of Green Power Panay Philippines Inc. (GPPPI) and Iloilo II Electric Cooperative (ILECO II) for the approval of the Electric Supply Agreement (ESA).   Click to View PDF File
Register to receive GGPC updates
ENTER YOUR EMAIL ADDRESS
Oil Price Dashboard
Crude Oil Price by OIL-PRICE.NET
Coal - Weekly Index
  NEWC Index RB Index DES ARA Index
06-Jan-2012 114.30 105.87 110.23
30-Dec-2011 115.47 106.57 112.39
23-Dec-2011 112.85 106.36 111.58
16-Dec-2011 110.28 101.95 110.61
Coal Weekly Index by globalCOAL


PDF Print E-mail Bookmark and Share


26 April 2010 in businessmirror.com.ph

‘Green’ laws perk up investor interest

Local and foreign investors expect new business opportunities to emerge in the Philippines as the country encourages the more energetic implementation of its “green” laws to develop environment-friendly technology not just because it is good for nature, but because it is also good for the bottom line.

For investors, a low carbon economy is attainable through renewable-energy sources. They said the future potential for such investments is fairly good for several renewable technologies—from small hydro, geothermal, biofuels, solar, wind and biomass.

David de Montaigne, president of British project-development firm Global Green Power Corp. (GGPC), said that in order to have a successful shift to a “green” economy in the Philippines, there is a need to have very careful planning to select the correct technologies and to place the correct and fair incentives to encourage investment.

“The Philippines is by far the most attractive country to invest within Asia. The investment climate through the Renewable Energy Act, ready supply of very talented engineers and experts, English spoken, and vast availability of biomass has attracted us to invest in the country,” said de Montaigne.

GGPC develops biomass renewable-energy power plants using sustainable biomass
resources such as agricultural crop and food- processing waste. It has targeted the Philippines for the construction and operation of biomass power-plant projects of between 17.5 to 35 megawatts (mW).

It now has three biomass-power projects expected to be fully operational by 2012 in Nueva Ecija, Iloilo and Bukidnon on an investment of about $192 million.

De Montaigne said the life-cycle costs of biomass-power plants are much less
expensive than fossil-fuel power plants if one takes into consideration the socioeconomic impacts it brings—use of local, indigenous, renewable fuel resources; delivery of an estimated P200 million in the first year of operation and P9 billion over 25 yearsper 17.5-MW plant to the local farming and host community through purchase of agriwaste for fuel and associated ancillary services such as transport and operations; and provision of base-load electricity to the Philippines like Panay Island, which suffered over 1,000 blackouts in 2008, making local economic development almost impossible.

In general, he said, all renewable energy solutions are more expensive than fossil fuel technology, “that is why a feed-in tariff is required to stimulate investment into the Philippines. Otherwise the new technology would not be developed. GGPC is a private company and so the project must be profitable to undertake, otherwise banks would not participate in the projects.”

De Montaigne said there is an urgent need to reduce consumption of power in tandem with developing renewable energy in developing countries to alleviate poverty and dispose of environmentally damaging agricultural waste.

A need for a global adjustment in the financial system that would facilitate more development in poorer countries is also urgently needed, he added.


 
Copyright © 2007 Global Green Power PLC All rights reserved